Istanbul Grand Airport was delivered at a scale and pace few programs ever attempt. I joined Kalyon Holding as a project controls and BIM engineer during construction.
I integrated Primavera P6 schedules with 3D models in BIM 360 to visualise sequencing and reduce schedule risk, and led 3D BIM coordination across multiple work scopes — resolving clashes against the baggage handling system (BHS) path in the federated model.
Critical-path analysis prioritised procurement on a compressed timeline, and I oversaw the substation, electrical switchgear and dedicated server-room cooling systems that support the BHS.
Highlights
- 4D sequencing: Primavera P6 schedules linked to BIM 360 models
- Clash resolution against the baggage handling system path in the federated model
- Oversight of BHS substation, switchgear and server-room cooling systems